1. 工程开工

Dear Sirs,

Sub: Acknowledgement of Notice to Commence

We acknowledge with thanks your notice to commence the Works issued pursuant to Clause 8 of
the Conditions of Contract, requesting us to commence as soon as is reasonably possible.

We confirm that the Commencement Date for the Works is .

We have begun to mobilize some equipment and personnel to the site of the Works and anticipate
commencing the Works no later than .


Yours faithfully,



2. 提交进度计划

Dear Sirs,

Sub: Submission of Program

As required under Clause 14 of the Conditions of Contract, we have pleasure in enclosing our
program for the Works, which is in such form and detail as you suggested in the meeting held at
your office on . You will note we have presented this program in both bar chart and
network form.

As recently requested by you, we also enclose a general description of the arrangements and
methods which we propose to adopt for the carrying out of the Works.

Yours faithfully,


3. 邀请函

Dear Sirs,

Sub: Letter of Invitation

According to the project schedule, a group of our engineers and technicians, 18 in total, will leave
China for this project shortly. In order to apply for the entry visa to your embassy in Beijing, you


are kindly requested to issue a letter of invitation for such personnel, whose pertinent information
is as follows:

NAME PASSPORT NO. DATE OF BIRTH PLACE OF BIRTH


Thank you in advance for your assistance and cooperation.

Yours faithfully,


4. 施工问题信件

Dear Sirs,

Sub: Data Found Incorrect for Setting Out the Works

With reference to your Site Plan showing dimensions for setting out the Works, we have to inform
you that after our own site survey, we have found the following errors and omissions on your
drawing:




Will you please issue a revised drawing showing correct dimensions so that we may proceed with
the setting-out of the Works? Since setting-out is schedule to commence on next Monday (May
20
th
2013), it is essential that we receive your revised drawing no later than this coming Friday.

Yours faithfully,


Dear Sirs,

Sub: Breakdown in Tower Crane

We regret to inform you that the progress of the Works is currently being, and is likely to continue
to be, delayed by a breakdown in the Tower Crane. Since this is of Japanese manufacture and the
local agents are unable to effect the repairs, technicians are being flown in from Japan and it will
be several days at least before it is again usable.

Needless to say, we are making every effort to overcome this problem in the meantime and we
shall be taking steps to ensure that completion of the Works is not delayed.

We shall inform you as soon as the problem is overcome and, in the meanwhile, please accept this


as the formal notice required by Clause 25 of the Conditions of the Contract.

Yours faithfully,


5. 回复业主问题邮件

Dear Sirs,

Sub: Request for Permission to Work at NightWeekends

In response to your letter to expedite progress of the Works and pursuant to Clause 46 of the
Conditions, we are writing to request that permission be given for work to continue on night and
weekend shifts.

Looking forward to your immediate permission.

Yours faithfully,


Dear Sirs,

Sub: Construction Acceleration

Further to our notice of delay dated and your letter of in reply, we note that
your letter purports to instruct us to take steps, following the cessation of the current exceptionally
adverse weather conditions, to accelerate so as to make up lost time.

We should respectfully point out to you that the Contract does not empower you so to instruct us
and we are not prepared to take any such steps except with express agreement of the Employer to
reimburse us for the additional costs involved plus a reasonable allowance for our overheads and
profit. Such an agreement would, of course, be supplementary to the Contract and its items will be
negotiated with the Employer to whom we are sending a copy of this letter.

Yours faithfully,


6. 业主回复的邮件

Dear Sirs,

Sub: Updating of Project Schedule

We have requested that you produce an updated schedule showing the actual condition of the


project.

The schedule that has been submitted by you shows only highlighted areas for the current month
and depicts all the work items as” in progress ”. Therefore, this updated schedule is not acceptable
to the Owner.

The properly updated schedule will show, for each activity, actual versus scheduled start date, and
actual percent complete compared to planned progress. You should then use such data to forecast
the probable completion dates of the behind schedule activities.

The data will allow the Owner to compare its analysis of the project with your analysis and to
thereby assist in planning future project events.

Yours faithfully,

Owner’s Representative


7.月进度报告邮件

Dear Sirs,

Sub: Format of Monthly Progress Report

In an effort to finalize the development of the format and ingredients of your Monthly progress
report identified in the Contract, please find below an outline of the contents required on a
monthly basis. The monthly progress report shall be submitted to the Owner on or before 10
th
of
each month.

1. A narrative description of the progress of the work for the preceding month.
Engineering Report
Construction Report
2. Status of the Materials and supplies necessary to support the scheduled on-going activities.
Material List
Equipment List
3. Status or actions related to approvals of licenses, certificates or permits identified in the
Contract Conditions that are required to support the work.
4. A presentation of work achieved towards the approved construction schedule.
Statused and updated MilestoneConstruction Schedule
Schedule recovery plans
5. Non-conformance Report
Project Master List of non-conformances
Identify deficiencies related to work in place for the previous month
Submit corrective plan


6. Manpower Report
Chinese staff and workers
Local workers
7. Subcontractor’s Report
Manpower
List of construction equipment
8. Problems and Concerns
9. Application for payment submittal

All the above sub-parts should be incorporated into one document known as the “Monthly
Progress Report “. Special attention should be given to this document for clarity, accuracy and
completeness.

We believe that this document will be most vital to both parties in assuring the success of this
project.

Your faithfully,

Engineer


7. 竣工邮件

Dear Sirs,

Sub: Notice of Tests on Completion Being Ready to Start

We are pleased to inform you that we will be ready to carry out the tests on completion after .
We will, as required by Clause 6 of the Conditions of the Contract, provide with you six complete
sets of “as built ” records, three copies of Operation and Maintenance Manuals prior to the
commencement of the Tests on Completion.

We are looking forward to your instructions regarding the dates for such tests, which should be
carried out within 14 days after the above mentioned date in accordance with Clause 9 of the
Conditions.

Yours faithfully,


8. 操作手册邮件

Dear Sirs,

Sub: Maintenance and Operation Manual


After review of the Maintenance and Operation Manual submitted by you, we regret that it is
found unacceptable, as the Manual, in our opinion, is not in sufficient detail for the Employer to
operate, maintain, dismantle, reassemble, adjust and repair Works. The following sections of the
Manual will have to be upgraded before we accept the manual:

Section C:
…………
Your attention is also drawn to the very fact that prior to the acceptance by us of such manuals, the
tests on completion will not be allowed to commence.

Yours faithfully,

Engineer

9. 申请移交邮件

Dear Sirs,

Sub: Application for Taking-over Certificate

We are writing to give you notice pursuant to Clause 48 of the Conditions that the whole of the
Works have now been substantially completed, and have satisfactorily passed all the Tests on
Completion specified in the Contract.

We undertake to finish any outstanding work with due expedition during the Defects Liability
Period. Should you think there exists any.

This letter of notice shall be deemed to be our request for you to issue the Taking-over Certificate
for the Works.

Yours faithfully,

Contractor


Dear Sirs,

Sub: Taking-over Certificate for Parts of the Work

With reference to your letter dated and all the circumstances considered, we now certify
pursuant to Clause 48 of the conditions that the following parts of the Works:
1.
……..
have been substantially completed and have passed all the relevant tests on completion


on , and were taken over by the Employer on the same day, together with the
responsibility for care and custody and the risk of loss thereof.

By the issue of this certificate, you are required to complete all the outstanding items listed in the
attachment hereto in these Parts of the permanent Works as soon as practicable.

This certificate does not relieve you of your obligations to complete the execution of the whole
Works in accordance with the Contract nor your obligations during the Defects Liability Period for
these parts of the Works, which started from the above date.

Yours faithfully,

Engineer

10. 不符合图纸或规范的工作邮件

Dear Sirs,

Sub: Non-conformance Report

Enclosed are two Non-conformance Reports, No.001 and 002. The Employer will use such form
to advise you of work not in accordance with the drawings or specifications.

The form requires your immediate action and shall be returned to us duly completed, describing
the action taken by you to correct the non-conformance work.

In the future, such forms will be directly sent to you without a covering letter.

You are hereby advised and alerted that we intend to closely observe the work in progress for
conformance to the drawings and specifications on file in the Engineer’s office. All work not in
accordance with such drawings and specifications will be logged on the Non- conformance Report
and will not qualify for payment until corrective action is complete.

Yours faithfully,

Engineer



11. 进度款邮件

Dear Sirs,

Sub: Notification of Non-payment


We refer to our monthly statement No. delivered to you on and regret to
advise you that we have not yet received the payment against this statement within the stipulated
period of 56 days pursuant to Sub- clause:14.7.

Under the circumstances and without prejudice to our interest entitlement at the rate specified in
the Appendix to tender, we request you to make the payment immediately. We will be compelled
to take such action as is appropriate under the Contract, should the payment be further delayed.

Yours faithfully,

Contractor

12. 保留金邮件

Dear Sirs,

Sub: Release of Retention Money

We write to acknowledge receipt of the Taking-over Certificate for Section D of the Works and
would ask that you certify the payment of the appropriate proportion of the Retention Money
pursuant to Clause 60 of the Conditions of Contract.

Yours faithfully,

Contractor

13. 竣工邮件

Dear Sirs,

Sub: Statement at Completion

We enclose our Statement at Completion together with supporting documents pursuant to Clause
14.10 of the Conditions of Contact.

This shows the final value of all work done in accordance with the Contract up to the date stated
in the Taking-over Certificate.

In addition, we have stated the further sums which we consider to be due together with an estimate
of amounts which we consider will become due to us under the Contract.

Yours faithfully,

Contract



14. 变更邮件

Dear Sirs,

Sub: Cost for Preparing the Change Proposal

With reference to your Request for Change Proposal, we are pleased to notify you of the
approximate cost of preparing the Change Proposal in accordance with the Conditions of Contract.
We acknowledge that your agreement to the cost of preparing the Change Proposal, in accordance
with Sub-clause 13.3, is required before estimating the cost for change work.

The following is the cost for preparation of Change Proposal:

(1) Engineering Amount
1) Engineer hrs X ratehr =
2) Draftsperson hrs X ratehr =
Subtotal hrs
Total Engineering Cost

(2) Other Cost

Total cost (1) +(2)

We look forward to your reply.

Yours faithfully,

Contractor

15. 口头指令确认

Dear Sirs,

Sub: Confirmation of Oral Instruction

In accordance with Sub-clauses 3.3 and 13.1 of the Conditions of Contract, we write to ask you to
confirm your oral instruction issued at site on to change the level of the Pump Station.
This has, in our opinion, constituted a change order.

We have to inform you that such an instruction will surely incur additional costs to us and we will
request you for compensation when the amount of such costs is known to us.

Yours faithfully,


Contractor